[ARCHIVED] EVERSOURCE CONSTRUCTION

eversource

UPDATED - AUGUST 31, 2023

HIGH IMPORTANCE
Final Pipe Staging Activity for Cross Street 

This notice is to update you regarding the ongoing work on Cross Street to install pipes underneath the Aberjona River. Crews completed the installation of two large diameter segments of pipe. This past Wednesday (8/30/23), crews completed the installation of smaller diameter interior pipes (1/2). Due to conditions in the field, the final installation of smaller diameter interior pipes (2/2) will be completed on Tuesday, September 5, 2023.

On Tuesday, September 5, Eversource crews will be transporting the final set of pipes onto Cross Street and installing these pipes under the Aberjona River via “pipe pullback” during daytime work hours. Once pipe pullback begins, it must continue until completion.

If you live on Cross Street and plan to leave your property throughout the day on Tuesday (Sept. 5) during work hours, please relocate your vehicle to Forest St., Marion St., or Washington St. on Monday night (Sept. 4).

Expect road closures on Tuesday, September 5, during work hours (5:00 a.m. to 4:00 p.m.)

On September 5, during the early morning, crews will transport pipe from Davidson Park to Cross Street between Forest St. and Washington St. 

During this activity, Cross Street will be CLOSED from Washington St. to Holton St. Police detail officers will maintain local access when possible.

  • Westbound traffic will be detoured back to Cross St. via Washington St., Montvale Ave., Green St., and Holton St.
  • Eastbound traffic will be detoured to Washington St. via Holton St., Green St., and Montvale Ave.
  • Residents with access needs must find alternate parking on Forest St., Marion St., or Washington St. (by Leonard Field)

1

During the second half of each day, crews will pull the pipe from Cross St. underground and into the previously excavated pit at the corner of Forest St.

During this activity, Cross St. from Forest St. to Washington St. will be open to local access only. Local access will be maintained for residents and businesses in the area. All other vehicles will utilize Forest St. as a detour.

  • If you are a property owner with access directly to Cross St. (between Forest St. and Washington St.), you will not be able to cross the road while pipe is staged in the roadway.
  • One lane of travel will be maintained from Forest St. toward Washington St.

2

Construction Hours

  • Work hours on September 5 are 5:00 a.m. to 4:00 p.m. Some activities may extend beyond normal work hours with Town approval.

Traffic Management

We coordinate closely with the Winchester Police Department and town officials to maintain a safe and effective flow of traffic. Vehicle detours will be in place and local access will be maintained. Access to Cross St. will be detoured utilizing Forest St and Green St.

If you have questions, please call Eric Sacchetti at 781-570-1228. If you have immediate questions in the field, please ask a police officer or crew construction member for assistance. Alternate parking is recommended at Washington St, Forest St, or Marion St. Vehicles will not be able to cross the double yellow line as pipe will be located along the middle of the road. Objects in the road will be clearly identified.

Stay Informed – Contact Us

• Phone: 1-833-836-0302
Email: ProjectInfoMa@eversource.com
Receive routine email updates: sign up at https://bit.ly/ESWWSignUp

Facebook Twitter Email

Other News in News Headlines

Untitled design (13)

HOUSING PRODUCTION PLAN

Posted on: November 28, 2023
Talk to the Town

TALK TO THE TOWN

Posted on: November 6, 2023
VOTE

ELECTION WORKERS NEEDED

Posted on: October 19, 2023
Untitled design (43)

ALL NIGHT PARKING BAN

Posted on: November 27, 2023